January 2009
Klystron tube water line repair by Jack Doskow.

April 2009
SESAME 3 degree neutron bender/polarizer installed

April 2009
SESAME Primary fligh path complete including mirrored guides and shileding. First version of triangle coils being installed.

May 2009
Klystron deck failures being debugged.

May 2009
SANS Detector electronics being debugged..

May 2009
Target failure blisters!

 

 

June 2009
SANS sample exchanger installed

 

July 2009
Target failure focusing.

July 2009
Target failure blisters!

July 2009
SESAME first beam.

August 2009
Klystron beam switch tube dies forcing 7 MeV operations throught the rest of 2009.

scope-27-Aug-2009.JPG

December 2009
Target failure 7 MeV, blisters on blisters